Case studyWater Technologies March 10, 2024 1 min read
RO Plant Capacity Expansion — 50 MLD Upgrade in Oman
## Background
Al-Ghubrah desalination plant, Oman's oldest large-scale SWRO facility, was commissioned in 2009 with a design capacity of 30 MLD. By 2022 demand had grown to require 50 MLD, and the site infrastructure — intake, pre-treatment, high-pressure pumping — was already in place.
## Challenge
Expanding capacity inside the existing footprint without a full plant outage, while meeting Oman's 2030 energy-efficiency targets (≤ 3.5 kWh/m³ net) and the regulator's continuous supply obligation.
## Approach
A phased membrane replacement programme swapped legacy 8" elements for high-rejection low-energy elements across 12 pressure vessel trains during planned maintenance windows. Isobaric energy-recovery devices replaced the old Pelton-wheel turbines on six trains.
## Results
- Output raised from 30 to 50 MLD (66 % increase)
- Specific energy consumption reduced from 4.1 to 3.37 kWh/m³
- No unplanned outage during the upgrade programme
- Payback on membrane investment: 28 months
The challenge
Expand capacity from 30 to 50 MLD inside an existing footprint without a full plant outage, while meeting national energy-efficiency targets.
The solution
Twelve pressure-vessel trains were retubed sequentially with new-generation 8" elements rated at 99.75 % NaCl rejection and 15 % lower feed pressure. Pelton turbines on six trains were replaced with isobaric ERDs raising energy recovery from 41 % to 53 %.
The results
Capacity +66 %, specific energy −18 %, no unplanned supply interruption, 28-month payback on capital.
Keys to success
Phased execution during planned maintenance windows; selection of high-rejection low-energy membrane elements; isobaric energy-recovery device retrofit.